A can lay a railway track between two stations in 16 days, and B can do the same job in 12 days. With the help of C, they did the job in only 4 days. In how many days can C alone do the job?

Answer as guest — Start Free Practice Test to earn Practice PointsHow to earn pointsAsk a question+3Answer a question+1Someone answers yours+1Your Q gets upvoted+1Pioneer bonus (first 5)+51 point = ₹1 discount on purchases, ask questions & climb the leaderboard!
Show answer and explanation

Answer: C. 9 3/5 days

(A+B+C)'s 1 day work = 1/4
A's 1 day work = 1/16, B's 1 day work = 1/12
C's 1 day work = 1/4 - (1/16 + 1/12) = 12/48 - 7/48 = 5/48
C alone takes 48/5 = 9 3/5 days.